| Action Date | Action Description |
|---|---|
| Apr 11, 2022 | Assent Application Received |
| Apr 15, 2022 | Administrative Review for Completeness |
| Apr 26, 2022 | Eng Team Review for Completeness |
| Apr 26, 2022 | Bio Team Review for Completeness |
| Apr 26, 2022 | Application Accepted |
| Apr 26, 2022 | Project Manager |
| Apr 26, 2022 | Category B assigned |
| May 11, 2022 | HPHC Historical Preservation No Effect |
| May 11, 2022 | HPHC Review Pending |
| Aug 31, 2022 | 30 day Public Notice Issued |
| Sep 30, 2022 | Public Notice End Date |
| Oct 31, 2022 | Mail Agenda Notice |
| Nov 01, 2022 | Plans Received |
| Nov 01, 2022 | Executive Signoff of Staff Reports |
| Nov 01, 2022 | Biologist Report |
| Nov 01, 2022 | Engineering Report |
| Nov 09, 2022 | Semi-Monthly Meeting Date Scheduled |
| Nov 09, 2022 | Council Approval Granted |
| Dec 13, 2022 | Legal Response/Decision |
| Dec 14, 2022 | Typist for Processing |
| Dec 14, 2022 | Executive Sign Off |
| Dec 14, 2022 | Sent to Photo Copy |
| Dec 14, 2022 | Permit Approved |
| Dec 14, 2022 | Stipulation Package by Engineer |
| Dec 15, 2022 | Permit Mailed |