| Action Date | Action Description |
|---|---|
| Apr 11, 2022 | CHA Worksheet received |
| Apr 11, 2022 | Assent Application Received |
| May 27, 2022 | Administrative Review for Completeness |
| Jun 08, 2022 | Bio Team Review for Completeness |
| Jun 08, 2022 | Application Accepted |
| Jun 13, 2022 | Project Manager |
| Jul 07, 2022 | HPHC Historical Preservation No Effect |
| Jul 07, 2022 | HPHC Review Pending |
| Oct 24, 2022 | Additional Information Received |
| Oct 28, 2022 | Typist for Processing |
| Oct 28, 2022 | Executive Sign Off |
| Oct 28, 2022 | Sent to Photo Copy |
| Oct 28, 2022 | Permit Approved |
| Oct 28, 2022 | Biologist Report |
| Oct 28, 2022 | Permit Mailed |
| Nov 09, 2022 | Land Evidence Date |
| Jun 16, 2023 | Note to File |
| Aug 03, 2023 | Modification Request |
| Aug 04, 2023 | Administrative Review for Completeness |
| Aug 07, 2023 | Additional Information Received |
| Aug 08, 2023 | Bio Team Review for Completeness |
| Aug 08, 2023 | Project Manager |
| Aug 23, 2023 | Biologist Report |
| Aug 25, 2023 | HPHC Historical Preservation No Effect |
| Sep 12, 2023 | Typist for Processing |
| Sep 12, 2023 | Executive Sign Off |
| Sep 12, 2023 | Sent to Photo Copy |
| Sep 12, 2023 | Modification Approved |
| Sep 18, 2023 | Permit Mailed |
| Sep 26, 2023 | Additional Information Received |
| Oct 03, 2023 | Land Evidence Date |