| Action Date | Action Description |
|---|---|
| May 02, 2022 | CHA Worksheet received |
| May 02, 2022 | Assent Application Received |
| May 10, 2022 | Administrative Review for Completeness |
| May 11, 2022 | Bio Team Review for Completeness |
| May 11, 2022 | Application Accepted |
| May 11, 2022 | Project Manager |
| May 17, 2022 | Additional Information Received |
| Jun 01, 2022 | Plans Received |
| Jun 20, 2022 | HPHC Historical Preservation No Effect |
| Jun 20, 2022 | HPHC Review Pending |
| Jul 06, 2022 | Additional Information Requested from Applicant |
| Aug 03, 2022 | Additional Information Received |
| Aug 04, 2022 | Additional Information Received |
| Sep 01, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Sep 08, 2022 | Correspondence Received |
| Sep 08, 2022 | Biologist Report |
| Sep 08, 2022 | Biologist Report |
| Sep 09, 2022 | Permit Mailed |
| Sep 09, 2022 | Typist for Processing |
| Sep 09, 2022 | Executive Sign Off |
| Sep 09, 2022 | Sent to Photo Copy |
| Sep 09, 2022 | Permit Approved |
| Sep 20, 2022 | Land Evidence Date |