| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 17, 2022 | Assent Application Received |
| May 19, 2022 | Administrative Review for Completeness |
| May 23, 2022 | Bio Team Review for Completeness |
| May 23, 2022 | Application Accepted |
| May 23, 2022 | Project Manager |
| May 23, 2022 | Category A* (Docks) |
| Jun 13, 2022 | HPHC Review Pending |
| Jun 13, 2022 | HPHC Historical Preservation No Effect |
| Aug 15, 2022 | 30 day Public Notice Issued |
| Aug 22, 2022 | US Army Corps of Engineers Approval Received |
| Sep 15, 2022 | Public Notice End Date |
| Oct 03, 2022 | Biologist Report |
| Oct 07, 2022 | Permit Mailed |
| Oct 07, 2022 | Typist for Processing |
| Oct 07, 2022 | Executive Sign Off |
| Oct 07, 2022 | Sent to Photo Copy |
| Oct 07, 2022 | Permit Approved |
| Oct 10, 2022 | Permit Mailed |
| Oct 20, 2022 | Land Evidence Date |