| Action Date | Action Description |
|---|---|
| Jun 17, 2022 | Maintenance Certification Request |
| Jun 23, 2022 | Administrative Review for Completeness |
| Jul 12, 2022 | Eng Team Review for Completeness |
| Jul 19, 2022 | Deficient Application - Owner Notification Sent |
| Jul 22, 2022 | Deficient Application Picked Up |
| Aug 23, 2022 | Deficiency Response Received |
| Aug 25, 2022 | Eng Team Review for Completeness |
| Aug 25, 2022 | Application Accepted |
| Aug 26, 2022 | Permit Approved |
| Aug 29, 2022 | Permit Mailed |