| Action Date | Action Description |
|---|---|
| Aug 11, 2022 | CHA Worksheet received |
| Aug 11, 2022 | Assent Application Received |
| Aug 16, 2022 | Administrative Review for Completeness |
| Aug 17, 2022 | Bio Team Review for Completeness |
| Aug 26, 2022 | Application Accepted |
| Sep 12, 2022 | 30 day Public Notice Issued |
| Sep 23, 2022 | HPHC Historical Preservation No Effect |
| Oct 12, 2022 | Public Notice End Date |
| Oct 21, 2022 | Public Notice End Date Extension Granted |
| Dec 27, 2022 | Mail Agenda Notice |
| Dec 28, 2022 | Engineering Report |
| Jan 10, 2023 | Council Approval Granted |
| Jan 10, 2023 | Semi-Monthly Meeting Date Scheduled |
| Jan 10, 2023 | Project Manager |
| Jan 10, 2023 | Biologist Report |
| Jan 11, 2023 | Stipulation Package from Biologist |
| Jan 11, 2023 | Stipulation Package by Engineer |
| Mar 01, 2023 | Legal Response/Decision |
| Mar 30, 2023 | Typist for Processing |
| Mar 30, 2023 | Permit Approved |
| Mar 31, 2023 | Executive Sign Off |
| Mar 31, 2023 | Permit Mailed |
| Apr 05, 2023 | Land Evidence Date |