| Action Date | Action Description |
|---|---|
| Aug 11, 2022 | Assent Application Received |
| Aug 17, 2022 | Administrative Review for Completeness |
| Aug 29, 2022 | Eng Team Review for Completeness |
| Aug 29, 2022 | Application Accepted |
| Sep 06, 2022 | Project Manager |
| Sep 13, 2022 | Engineering Report |
| Oct 05, 2022 | HPHC Historical Preservation No Effect |
| Oct 17, 2022 | Finding Of No Significant Impact (FONSI) |
| Oct 17, 2022 | Permit Mailed |