| Action Date | Action Description |
|---|---|
| Aug 24, 2022 | CHA Worksheet received |
| Aug 24, 2022 | Assent Application Received |
| Aug 25, 2022 | Administrative Review for Completeness |
| Sep 01, 2022 | Bio Team Review for Completeness |
| Sep 06, 2022 | Deficient Application - Owner Notification Sent |
| Sep 16, 2022 | Deficient Application Picked Up |
| Oct 12, 2022 | Deficiency Response Received |
| Oct 21, 2022 | Bio Team Review for Completeness |
| Oct 21, 2022 | Application Accepted |
| Oct 24, 2022 | Project Manager |
| Nov 25, 2022 | HPHC Historical Preservation No Effect |
| Dec 16, 2022 | Additional Information Received |
| Jan 19, 2023 | Additional Information Received |
| Jan 24, 2023 | Biologist Report |
| Feb 09, 2023 | Typist for Processing |
| Feb 09, 2023 | Executive Sign Off |
| Feb 09, 2023 | Sent to Photo Copy |
| Feb 09, 2023 | Permit Approved |
| Feb 13, 2023 | Permit Mailed |
| Feb 20, 2023 | Land Evidence Date |