| Action Date | Action Description |
|---|---|
| Sep 23, 2022 | Assent Application Received |
| Sep 27, 2022 | Administrative Review for Completeness |
| Sep 29, 2022 | Bio Team Review for Completeness |
| Sep 29, 2022 | Application Accepted |
| Oct 03, 2022 | Project Manager |
| Oct 04, 2022 | HPHC Historical Preservation No Effect |
| Oct 26, 2022 | Biologist Report |
| Nov 02, 2022 | Typist for Processing |
| Nov 02, 2022 | Executive Sign Off |
| Nov 02, 2022 | Sent to Photo Copy |
| Nov 02, 2022 | Permit Approved |
| Nov 02, 2022 | Permit Mailed |
| Feb 06, 2023 | Land Evidence Date |