| Action Date | Action Description |
|---|---|
| Dec 21, 2022 | Maintenance Certification Request |
| Dec 27, 2022 | Administrative Review for Completeness |
| Jan 11, 2023 | Bio Team Review for Completeness |
| Jan 12, 2023 | Additional Information Requested from Applicant |
| Jan 24, 2023 | Phone Call |
| Jan 24, 2023 | Application Accepted |
| Jan 24, 2023 | Project Manager |
| Jan 24, 2023 | Bio Team Review for Completeness |
| Jan 25, 2023 | Additional Information Received |
| Jan 27, 2023 | HPHC Historical Preservation No Effect |
| Jan 30, 2023 | Additional Information Received |
| Feb 17, 2023 | Biologist Report |
| Feb 17, 2023 | Permit Approved |
| Feb 22, 2023 | Permit Mailed |