| Action Date | Action Description |
|---|---|
| Mar 07, 2023 | Freshwater Wetlands Application - New - received |
| Mar 09, 2023 | Administrative Review for Completeness |
| Mar 13, 2023 | Bio Team Review for Completeness |
| Mar 13, 2023 | Project Manager |
| Mar 13, 2023 | Application Accepted |
| Mar 22, 2023 | HPHC Historical Preservation No Effect |
| May 03, 2023 | Biologist Report |
| May 04, 2023 | Typist for Processing |
| May 04, 2023 | Executive Sign Off |
| May 04, 2023 | Sent to Photo Copy |
| May 04, 2023 | Permit Approved |
| May 11, 2023 | Permit Mailed |
| Oct 06, 2023 | Land Evidence Date |