| Action Date | Action Description |
|---|---|
| May 31, 2023 | Assent Application Received |
| Jun 05, 2023 | Administrative Review for Completeness |
| Jun 13, 2023 | Bio Team Review for Completeness |
| Jun 13, 2023 | Deficient Application - Owner Notification Sent |
| Jun 21, 2023 | Phone Call |
| Jul 19, 2023 | Deficiency Response Received |
| Jul 21, 2023 | Bio Team Review for Completeness |
| Jul 21, 2023 | Application Accepted |
| Jul 21, 2023 | Project Manager |
| Jul 31, 2023 | HPHC Historical Preservation No Effect |
| Sep 29, 2023 | Biologist Report |
| Oct 05, 2023 | Typist for Processing |
| Oct 05, 2023 | Executive Sign Off |
| Oct 05, 2023 | Sent to Photo Copy |
| Oct 05, 2023 | Permit Approved |
| Oct 06, 2023 | Permit Mailed |
| Nov 01, 2023 | Land Evidence Date |