| Action Date | Action Description |
|---|---|
| Jun 21, 2023 | Maintenance Certification Request |
| Jun 27, 2023 | Administrative Review for Completeness |
| Jul 26, 2023 | Eng Team Review for Completeness |
| Jul 31, 2023 | Deficient Application - Owner Notification Sent |
| Aug 04, 2023 | Deficiency Response Received |
| Aug 07, 2023 | Eng Team Review for Completeness |
| Aug 07, 2023 | Application Accepted |
| Aug 07, 2023 | Project Manager |
| Aug 17, 2023 | Engineering Report |
| Aug 21, 2023 | Typist for Processing |
| Aug 21, 2023 | Executive Sign Off |
| Aug 21, 2023 | Sent to Photo Copy |
| Aug 21, 2023 | Permit Approved |
| Aug 22, 2023 | Permit Mailed |
| Aug 30, 2023 | Land Evidence Date |
| Sep 19, 2023 | Additional Information Received |