| Action Date | Action Description |
|---|---|
| Jul 06, 2023 | Assent Application Received |
| Jul 11, 2023 | Administrative Review for Completeness |
| Jul 19, 2023 | Bio Team Review for Completeness |
| Jul 19, 2023 | Application Accepted |
| Jul 19, 2023 | Project Manager |
| Jul 31, 2023 | HPHC Historical Preservation No Effect |
| Sep 22, 2023 | 30 day Public Notice Issued |
| Oct 22, 2023 | Public Notice End Date |
| Nov 07, 2023 | Correspondence Received |
| Jan 31, 2024 | Plans Received |
| Feb 09, 2024 | Dock/1.1.6 Review approval |
| Feb 14, 2024 | Biologist Report |
| Feb 16, 2024 | Typist for Processing |
| Feb 16, 2024 | Executive Sign Off |
| Feb 16, 2024 | Sent to Photo Copy |
| Feb 16, 2024 | Permit Approved |
| Feb 20, 2024 | Permit Mailed |
| Feb 23, 2024 | Land Evidence Date |
| Aug 19, 2024 | Modification Request |
| Aug 22, 2024 | Administrative Review for Completeness |
| Aug 28, 2024 | Bio Team Review for Completeness |
| Aug 28, 2024 | Project Manager |
| Aug 28, 2024 | Application Accepted |
| Aug 29, 2024 | US Army Corps of Engineers Approval Received |
| Sep 12, 2024 | 30 day Public Notice Issued |
| Sep 18, 2024 | HPHC Historical Preservation No Effect |
| Oct 12, 2024 | Public Notice End Date |
| Oct 16, 2024 | Biologist Report |
| Oct 21, 2024 | Typist for Processing |
| Oct 21, 2024 | Modification Approved |
| Oct 21, 2024 | Modification mailed |
| May 30, 2025 | Land Evidence Date |
| Jun 26, 2025 | Additional Information Received |
| Aug 21, 2025 | Additional Information Received |
| Aug 21, 2025 | Dock Post-Construction Certification by Engineer received. |