| Action Date | Action Description |
|---|---|
| Aug 09, 2023 | Assent Application Received |
| Aug 11, 2023 | Administrative Review for Completeness |
| Aug 24, 2023 | Bio Team Review for Completeness |
| Aug 24, 2023 | Application Accepted |
| Aug 24, 2023 | Project Manager |
| Sep 14, 2023 | HPHC Historical Preservation No Effect |
| Sep 25, 2023 | Executive Sign Off |
| Sep 25, 2023 | Sent to Photo Copy |
| Sep 29, 2023 | Additional Information Requested from Applicant |
| Oct 06, 2023 | Additional Information Received |
| Oct 25, 2023 | Typist for Processing |
| Oct 25, 2023 | Biologist Report |
| Oct 25, 2023 | Permit Approved |
| Nov 01, 2023 | Permit Mailed |
| Nov 14, 2023 | Land Evidence Date |