| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Sep 12, 2023 | Maintenance Certification Request |
| Sep 14, 2023 | Administrative Review for Completeness |
| Sep 21, 2023 | Eng Team Review for Completeness |
| Sep 21, 2023 | Application Accepted |
| Sep 21, 2023 | Project Manager |
| Oct 12, 2023 | Engineering Report |
| Nov 09, 2023 | Typist for Processing |
| Nov 09, 2023 | Executive Sign Off |
| Nov 09, 2023 | Sent to Photo Copy |
| Nov 09, 2023 | Permit Approved |
| Nov 10, 2023 | HPHC Historical Preservation No Effect |
| Nov 14, 2023 | Permit Mailed |