| Action Date | Action Description |
|---|---|
| Jan 02, 2024 | Assent Application Received |
| Jan 05, 2024 | Administrative Review for Completeness |
| Jan 30, 2024 | Eng Team Review for Completeness |
| Jan 30, 2024 | Deficient Application - Owner Notification Sent |
| Aug 28, 2024 | Deficiency Response Received |
| Sep 04, 2024 | Eng Team Review for Completeness |
| Sep 04, 2024 | Application Accepted |
| Sep 04, 2024 | Project Manager |
| Sep 19, 2024 | HPHC Historical Preservation No Effect |
| Oct 10, 2024 | Engineering Report |
| Oct 11, 2024 | Typist for Processing |
| Oct 11, 2024 | Executive Sign Off |
| Oct 11, 2024 | Sent to Photo Copy |
| Oct 11, 2024 | Permit Approved |
| Oct 15, 2024 | Permit Mailed |
| Jan 10, 2025 | Additional Information Received |