| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer Required. | |
| Jan 19, 2024 | Assent Application Received |
| Jan 25, 2024 | Administrative Review for Completeness |
| Jan 26, 2024 | Bio Team Review for Completeness |
| Jan 26, 2024 | Application Accepted |
| Jan 26, 2024 | Project Manager |
| Jan 26, 2024 | Category A* (Docks) |
| Feb 09, 2024 | HPHC Historical Preservation No Effect |
| Mar 14, 2024 | 30 day Public Notice Issued |
| Apr 14, 2024 | Public Notice End Date |
| May 10, 2024 | Dock/1.1.6 Review approval |
| May 14, 2024 | Biologist Report |
| May 28, 2024 | Typist for Processing |
| May 28, 2024 | Executive Sign Off |
| May 28, 2024 | Sent to Photo Copy |
| May 28, 2024 | Permit Approved |
| May 30, 2024 | Permit Mailed |
| Oct 07, 2024 | Land Evidence Date |