| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jan 26, 2024 | Assent Application Received |
| Feb 01, 2024 | Administrative Review for Completeness |
| Feb 12, 2024 | Bio Team Review for Completeness |
| Feb 12, 2024 | Project Manager |
| Feb 14, 2024 | Application Accepted |
| Feb 14, 2024 | Category A* (Docks) |
| Feb 16, 2024 | HPHC Historical Preservation No Effect |
| Apr 12, 2024 | Additional Information Received |
| May 31, 2024 | 30 day Public Notice Issued |
| Jun 30, 2024 | Public Notice End Date |
| Jul 23, 2024 | Comments Received |
| Jul 24, 2024 | Comments Received |
| Jul 30, 2024 | Public Notice End Date Extension Granted |
| Sep 10, 2024 | Plans Received |
| Sep 16, 2024 | Engineering Report |
| Sep 16, 2024 | Biologist Report |
| Sep 17, 2024 | Typist for Processing |
| Sep 17, 2024 | Executive Sign Off |
| Sep 17, 2024 | Sent to Photo Copy |
| Sep 17, 2024 | Permit Approved |
| Sep 19, 2024 | Permit Mailed |
| May 28, 2025 | Land Evidence Date |