| Action Date | Action Description |
|---|---|
| Engineering Report | |
| Biologist Report | |
| Jan 29, 2024 | Assent Application Received |
| Feb 02, 2024 | Administrative Review for Completeness |
| Feb 26, 2024 | Eng Team Review for Completeness |
| Feb 26, 2024 | Application Accepted |
| Feb 26, 2024 | Project Manager |
| Feb 26, 2024 | Category A* (Docks) |
| Mar 08, 2024 | HPHC Historical Preservation No Effect |
| Sep 03, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Jan 30, 2025 | 30 day Public Notice Issued |
| Feb 26, 2025 | Note to File |
| Feb 26, 2025 | Correspondence Received |
| Feb 26, 2025 | Additional Information Requested from Applicant |
| Feb 27, 2025 | Public Notice End Date Extension Granted |
| Mar 02, 2025 | Public Notice End Date |
| Mar 05, 2025 | US Army Corps of Engineers Project Number received. |
| Mar 20, 2025 | Additional Information Received |
| Mar 24, 2025 | Objections/Comments Received |
| Mar 24, 2025 | Public Notice End Date |
| Mar 24, 2025 | Note to File |
| Apr 29, 2025 | 30-Day Notification of Cancellation letter |
| Jul 01, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Sep 05, 2025 | Correspondence Received |
| Sep 05, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Sep 09, 2025 | Correspondence Received |
| Sep 12, 2025 | Additional Information Requested from Applicant |