| Action Date | Action Description |
|---|---|
| Feb 15, 2024 | Assent Application Received |
| Feb 20, 2024 | Administrative Review for Completeness |
| Feb 23, 2024 | Eng Team Review for Completeness |
| Feb 23, 2024 | Project Manager |
| Feb 23, 2024 | Application Accepted |
| Apr 04, 2024 | HPHC Historical Preservation No Effect |
| Apr 29, 2024 | Biologist Report |
| Apr 29, 2024 | Engineering Report |
| Apr 30, 2024 | Typist for Processing |
| Apr 30, 2024 | Executive Sign Off |
| Apr 30, 2024 | Sent to Photo Copy |
| Apr 30, 2024 | Permit Approved |
| May 01, 2024 | Permit Mailed |
| Aug 01, 2024 | Commencement of Work Notice received |