| Action Date | Action Description |
|---|---|
| HPHC Review Pending | |
| Feb 27, 2024 | Assent Application Received |
| Mar 05, 2024 | Administrative Review for Completeness |
| Mar 22, 2024 | Eng Team Review for Completeness |
| Mar 22, 2024 | Application Accepted |
| Mar 22, 2024 | Project Manager |
| Sep 11, 2024 | Permit Approved |
| Oct 10, 2024 | Engineering Report |
| Oct 11, 2024 | Typist for Processing |
| Oct 11, 2024 | Executive Sign Off |
| Oct 11, 2024 | Sent to Photo Copy |
| Oct 11, 2024 | Permit Approved |
| Dec 04, 2024 | Land Evidence Date |