| Action Date | Action Description |
|---|---|
| US Army Corps of Engineers Approval Required | |
| Dock Post-Construction Certification by Engineer received. | |
| Feb 29, 2024 | Assent Application Received |
| Mar 06, 2024 | Administrative Review for Completeness |
| Mar 08, 2024 | Bio Team Review for Completeness |
| Mar 08, 2024 | Deficient Application - Owner Notification Sent |
| Mar 08, 2024 | Category A* (Docks) |
| Mar 22, 2024 | Note to File |
| Apr 17, 2024 | Note to File |
| Jul 31, 2024 | Deficiency Response Received |
| Aug 06, 2024 | Bio Team Review for Completeness |
| Aug 07, 2024 | Application Accepted |
| Aug 07, 2024 | Project Manager |
| Aug 16, 2024 | HPHC Historical Preservation No Effect |
| Sep 18, 2024 | 30 day Public Notice Issued |
| Oct 18, 2024 | Public Notice End Date |
| Nov 12, 2024 | Plans Received |
| Dec 20, 2024 | Dock Meeting -- Approval |
| Dec 27, 2024 | Biologist Report |
| Dec 30, 2024 | Typist for Processing |
| Dec 30, 2024 | Executive Sign Off |
| Dec 30, 2024 | Sent to Photo Copy |
| Dec 30, 2024 | Permit Approved |
| Jan 03, 2025 | Permit Mailed |
| Jan 28, 2025 | Land Evidence Date |