| Action Date | Action Description |
|---|---|
| Mar 01, 2024 | CHA Worksheet received |
| Mar 01, 2024 | Assent Application Received |
| Mar 07, 2024 | Administrative Review for Completeness |
| Mar 13, 2024 | Bio Team Review for Completeness |
| Mar 13, 2024 | Project Manager |
| Mar 13, 2024 | Additional Information Requested from Applicant |
| Mar 13, 2024 | Application Accepted |
| Apr 03, 2024 | Plans Received |
| Apr 16, 2024 | HPHC Historical Preservation No Effect |
| Aug 02, 2024 | Additional Information Received |
| Aug 28, 2024 | Biologist Report |
| Aug 29, 2024 | Typist for Processing |
| Aug 29, 2024 | Executive Sign Off |
| Aug 29, 2024 | Sent to Photo Copy |
| Aug 29, 2024 | Permit Approved |
| Sep 03, 2024 | Permit Mailed |
| Sep 10, 2024 | Land Evidence Date |
| Oct 24, 2024 | Commencement of Work Notice received |