| Action Date | Action Description |
|---|---|
| Apr 01, 2024 | Maintenance Certification Request |
| Apr 05, 2024 | Administrative Review for Completeness |
| Jun 06, 2024 | Eng Team Review for Completeness |
| Jun 06, 2024 | Bio Team Review for Completeness |
| Jun 06, 2024 | Application Accepted |
| Jun 06, 2024 | Project Manager |
| Jun 12, 2024 | Fee Waiver Granted |
| Jun 14, 2024 | Plans Received |
| Jul 01, 2024 | HPHC Historical Preservation No Effect |
| Jul 11, 2024 | Biologist Report |
| Jul 19, 2024 | Typist for Processing |
| Jul 19, 2024 | Executive Sign Off |
| Jul 19, 2024 | Sent to Photo Copy |
| Jul 19, 2024 | Permit Approved |
| Jul 23, 2024 | Permit Mailed |
| Oct 18, 2024 | Land Evidence Date |