| Action Date | Action Description |
|---|---|
| Apr 04, 2024 | Assent Application Received |
| Apr 10, 2024 | Administrative Review for Completeness |
| Apr 12, 2024 | Bio Team Review for Completeness |
| Apr 12, 2024 | Application Accepted |
| Apr 12, 2024 | Project Manager |
| Apr 19, 2024 | HPHC Historical Preservation No Effect |
| Jun 07, 2024 | Biologist Report |
| Jul 22, 2024 | Geologist Report |
| Jul 22, 2024 | Typist for Processing |
| Jul 22, 2024 | Executive Sign Off |
| Jul 22, 2024 | Sent to Photo Copy |
| Jul 22, 2024 | Permit Approved |
| Jul 23, 2024 | Permit Mailed |
| Aug 02, 2024 | Commencement of Work Notice received |