| Action Date | Action Description |
|---|---|
| Apr 25, 2024 | Assent Application Received |
| Apr 30, 2024 | Administrative Review for Completeness |
| May 07, 2024 | Bio Team Review for Completeness |
| May 08, 2024 | Deficient Application - Owner Notification Sent |
| Jul 12, 2024 | Deficiency Response Received |
| Jul 19, 2024 | Bio Team Review for Completeness |
| Jul 19, 2024 | Application Accepted |
| Jul 23, 2024 | Project Manager |
| Aug 07, 2024 | HPHC Historical Preservation No Effect |
| Nov 06, 2024 | Additional Information Received |
| Nov 12, 2024 | Typist for Processing |
| Nov 12, 2024 | Executive Sign Off |
| Nov 12, 2024 | Sent to Photo Copy |
| Nov 12, 2024 | Permit Approved |
| Nov 12, 2024 | Biologist Report |
| Nov 14, 2024 | Permit Mailed |
| Jan 31, 2025 | Land Evidence Date |
| Mar 18, 2025 | Assent Requirement |