| Action Date | Action Description |
|---|---|
| May 02, 2024 | Assent Application Received |
| May 08, 2024 | Administrative Review for Completeness |
| May 21, 2024 | Eng Team Review for Completeness |
| May 21, 2024 | Project Manager |
| May 22, 2024 | Application Accepted |
| Jun 24, 2024 | HPHC Historical Preservation No Effect |
| Jul 22, 2024 | Typist for Processing |
| Jul 22, 2024 | Executive Sign Off |
| Jul 22, 2024 | Sent to Photo Copy |
| Jul 22, 2024 | Permit Approved |
| Jul 22, 2024 | Engineering Report |
| Jul 23, 2024 | Permit Mailed |