| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Aug 30, 2023 | Meeting Held |
| May 17, 2024 | CHA Worksheet received |
| May 17, 2024 | Assent Application Received |
| May 22, 2024 | Administrative Review for Completeness |
| Jun 06, 2024 | Eng Team Review for Completeness |
| Jun 06, 2024 | Bio Team Review for Completeness |
| Jun 06, 2024 | Project Manager |
| Jun 06, 2024 | Application Accepted |
| Nov 26, 2024 | Note to File |
| Dec 12, 2024 | Additional Information Requested from Applicant |
| Jan 31, 2025 | 30 day Public Notice Issued |
| Feb 03, 2025 | HPHC Historical Preservation No Effect |
| Feb 05, 2025 | Correspondence Received |
| Mar 03, 2025 | Objections/Comments Received |
| Mar 03, 2025 | Objections/Comments Received |
| Mar 03, 2025 | Public Notice End Date |
| Aug 22, 2025 | Additional Information Received |
| Oct 10, 2025 | Correspondence Received |
| Oct 10, 2025 | Additional Information Requested from Applicant |
| Oct 14, 2025 | Correspondence Received |
| Oct 15, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Oct 15, 2025 | Phone Call |
| Oct 15, 2025 | Correspondence Received |
| Oct 16, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Oct 17, 2025 | Biologist Report |
| Oct 17, 2025 | Engineering Report |
| Oct 21, 2025 | Typist for Processing |
| Oct 21, 2025 | Executive Sign Off |
| Oct 21, 2025 | Sent to Photo Copy |
| Oct 21, 2025 | Permit Approved |
| Oct 21, 2025 | Permit Mailed |