| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer Required. | |
| Jun 27, 2024 | Assent Application Received |
| Jul 01, 2024 | Administrative Review for Completeness |
| Jul 02, 2024 | Eng Team Review for Completeness |
| Jul 02, 2024 | Project Manager |
| Jul 02, 2024 | Application Accepted |
| Jul 31, 2024 | 30 day Public Notice Issued |
| Aug 16, 2024 | HPHC Historical Preservation No Effect |
| Aug 22, 2024 | Correspondence Received |
| Aug 23, 2024 | Correspondence Received |
| Aug 31, 2024 | Public Notice End Date |
| Sep 27, 2024 | Plans Received |
| Oct 29, 2024 | Engineering Report |
| Nov 01, 2024 | Typist for Processing |
| Nov 01, 2024 | Executive Sign Off |
| Nov 01, 2024 | Sent to Photo Copy |
| Nov 01, 2024 | Permit Approved |
| Nov 04, 2024 | Permit Mailed |
| May 28, 2025 | Land Evidence Date |