| Action Date | Action Description |
|---|---|
| Aug 26, 2024 | Assent Application Received |
| Aug 30, 2024 | Administrative Review for Completeness |
| Sep 10, 2024 | Bio Team Review for Completeness |
| Sep 10, 2024 | Deficient Application - Owner Notification Sent |
| Nov 06, 2024 | Deficiency Response Received |
| Nov 15, 2024 | Bio Team Review for Completeness |
| Nov 15, 2024 | Application Accepted |
| Nov 15, 2024 | Project Manager |
| Dec 09, 2024 | HPHC Historical Preservation No Effect |
| Jun 03, 2025 | Biologist Report |
| Jun 09, 2025 | Typist for Processing |
| Jun 09, 2025 | Executive Sign Off |
| Jun 09, 2025 | Sent to Photo Copy |
| Jun 09, 2025 | Permit Approved |
| Jun 10, 2025 | Permit Mailed |
| Jul 17, 2025 | Land Evidence Date |