| Action Date | Action Description |
|---|---|
| Sep 06, 2024 | Assent Application Received |
| Sep 10, 2024 | Administrative Review for Completeness |
| Sep 11, 2024 | Bio Team Review for Completeness |
| Sep 11, 2024 | Project Manager |
| Sep 11, 2024 | Application Accepted |
| Sep 17, 2024 | Additional Information Requested from Applicant |
| Sep 19, 2024 | HPHC Historical Preservation No Effect |
| Sep 24, 2024 | Plans Received |
| Oct 09, 2024 | Biologist Report |
| Oct 16, 2024 | Finding Of No Significant Impact (FONSI) |
| Oct 17, 2024 | Permit Mailed |
| Mar 04, 2025 | Modification Request |
| Mar 11, 2025 | Administrative Review for Completeness |
| Mar 18, 2025 | Bio Team Review for Completeness |
| Mar 18, 2025 | Modification Approved |
| Mar 18, 2025 | Modification mailed |