| Action Date | Action Description |
|---|---|
| Sep 24, 2024 | Assent Application Received |
| Sep 30, 2024 | Administrative Review for Completeness |
| Oct 01, 2024 | Bio Team Review for Completeness |
| Oct 01, 2024 | Project Manager |
| Oct 01, 2024 | Application Accepted |
| Oct 23, 2024 | HPHC Historical Preservation No Effect |
| Nov 08, 2024 | Plans Received |
| Nov 19, 2024 | 30 day Public Notice Issued |
| Dec 19, 2024 | Public Notice End Date |
| Dec 20, 2024 | Dock Meeting -- Approval |
| Dec 22, 2024 | Additional Information Received |
| Jan 08, 2025 | Objections/Comments Received |
| Jan 10, 2025 | Comments Received |
| Jan 10, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Jan 29, 2025 | Dock Meeting -- To Council |
| Jan 31, 2025 | Mail Agenda Notice |
| Feb 04, 2025 | Biologist Report |
| Feb 11, 2025 | Semi-Monthly Meeting Held |
| Feb 11, 2025 | Council Approval Granted |
| Feb 11, 2025 | Semi-Monthly Meeting Date Scheduled |
| Feb 12, 2025 | Stipulation Package from Biologist |
| Mar 26, 2025 | US Army Corps of Engineers Approval Received |
| Mar 31, 2025 | Legal Response/Decision |
| Apr 30, 2025 | Typist for Processing |
| Apr 30, 2025 | Permit Approved |
| May 06, 2025 | Permit Mailed |
| May 14, 2025 | Commencement of Work Notice received |
| Jun 24, 2025 | Land Evidence Date |
| Aug 12, 2025 | Dock Post-Construction Certification by Engineer received. |
| Aug 12, 2025 | Additional Information Received |