| Action Date | Action Description |
|---|---|
| Assent Requirement | |
| Sep 30, 2024 | Assent Application Received |
| Oct 01, 2024 | Administrative Review for Completeness |
| Oct 08, 2024 | Bio Team Review for Completeness |
| Oct 08, 2024 | Application Accepted |
| Oct 08, 2024 | Project Manager |
| Oct 23, 2024 | HPHC Historical Preservation No Effect |
| Nov 19, 2024 | Additional Information Requested from Applicant |
| Jan 28, 2025 | Plans Received |
| Jan 31, 2025 | Biologist Report |
| Feb 07, 2025 | Typist for Processing |
| Feb 17, 2025 | Executive Sign Off |
| Feb 17, 2025 | Sent to Photo Copy |
| Feb 17, 2025 | Permit Approved |
| Feb 19, 2025 | Permit Mailed |
| Feb 25, 2025 | Land Evidence Date |
| May 15, 2025 | Commencement of Work Notice received |