| Action Date | Action Description |
|---|---|
| Oct 01, 2024 | CHA Worksheet received |
| Oct 01, 2024 | Assent Application Received |
| Oct 02, 2024 | Administrative Review for Completeness |
| Oct 04, 2024 | Bio Team Review for Completeness |
| Oct 04, 2024 | Application Accepted |
| Oct 04, 2024 | Project Manager |
| Oct 28, 2024 | HPHC Historical Preservation No Effect |
| Nov 14, 2024 | Additional Information Requested from Applicant |
| Dec 11, 2024 | Additional Information Received |
| Dec 31, 2024 | Plans Received |
| Jan 03, 2025 | Biologist Report |
| Jan 07, 2025 | Typist for Processing |
| Jan 07, 2025 | Executive Sign Off |
| Jan 07, 2025 | Sent to Photo Copy |
| Jan 07, 2025 | Permit Approved |
| Jan 10, 2025 | Permit Mailed |
| Jan 23, 2025 | Land Evidence Date |