| Action Date | Action Description |
|---|---|
| Biologist Report | |
| Engineering Report | |
| Oct 04, 2024 | Assent Application Received |
| Oct 04, 2024 | CHA Worksheet received |
| Oct 08, 2024 | Administrative Review for Completeness |
| Oct 17, 2024 | Bio Team Review for Completeness |
| Oct 17, 2024 | Application Accepted |
| Oct 17, 2024 | Project Manager |
| Jan 06, 2025 | HPHC Historical Preservation Comments/Concerns |
| Jan 31, 2025 | 30 day Public Notice Issued |
| Jan 31, 2025 | HPHC Historical Preservation Comments/Concerns |
| Feb 05, 2025 | Correspondence Received |
| Feb 14, 2025 | Objections/Comments Received |
| Mar 03, 2025 | Objections/Comments Received |
| Mar 03, 2025 | Public Notice End Date |
| Mar 04, 2025 | Comments Received |
| Mar 05, 2025 | Correspondence Received |
| Oct 22, 2025 | Correspondence Mailed/Faxed/E-mailed |