| Action Date | Action Description |
|---|---|
| Oct 04, 2024 | Assent Application Received |
| Oct 09, 2024 | Administrative Review for Completeness |
| Oct 09, 2024 | Bio Team Review for Completeness |
| Oct 09, 2024 | Project Manager |
| Oct 09, 2024 | Application Accepted |
| Oct 17, 2024 | 30 day Public Notice Issued |
| Oct 23, 2024 | HPHC Historical Preservation No Effect |
| Nov 17, 2024 | Public Notice End Date |
| Dec 20, 2024 | Dock Meeting -- Approval |
| Dec 31, 2024 | Biologist Report |
| Jan 03, 2025 | Permit Mailed |
| Jan 03, 2025 | Typist for Processing |
| Jan 03, 2025 | Executive Sign Off |
| Jan 03, 2025 | Sent to Photo Copy |
| Jan 03, 2025 | Permit Approved |
| Jan 17, 2025 | Land Evidence Date |
| Jan 28, 2025 | US Army Corps of Engineers Approval Required |
| Jun 16, 2025 | Commencement of Work Notice received |
| Aug 04, 2025 | Additional Information Received |
| Aug 06, 2025 | Dock Post-Construction Certification by Engineer received. |