| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Oct 10, 2024 | Assent Application Received |
| Oct 15, 2024 | Administrative Review for Completeness |
| Oct 17, 2024 | Additional Information Received |
| Nov 21, 2024 | Application Accepted |
| Nov 21, 2024 | Bio Team Review for Completeness |
| Nov 21, 2024 | Project Manager |
| Nov 29, 2024 | 30 day Public Notice Issued |
| Dec 13, 2024 | HPHC Historical Preservation No Effect |
| Dec 29, 2024 | Public Notice End Date |
| Mar 03, 2025 | Biologist Report |
| Mar 05, 2025 | Typist for Processing |
| Mar 05, 2025 | Executive Sign Off |
| Mar 05, 2025 | Sent to Photo Copy |
| Mar 05, 2025 | Permit Approved |
| Mar 10, 2025 | Permit Mailed |
| Mar 28, 2025 | Land Evidence Date |
| Aug 28, 2025 | Additional Information Received |