| Action Date | Action Description |
|---|---|
| Oct 11, 2024 | Assent Application Received |
| Oct 18, 2024 | Administrative Review for Completeness |
| Oct 23, 2024 | Bio Team Review for Completeness |
| Oct 25, 2024 | Deficient Application - Owner Notification Sent |
| Dec 02, 2024 | Deficiency Response Received |
| Dec 12, 2024 | Additional Information Requested from Applicant |
| Dec 18, 2024 | Application Accepted |
| Dec 18, 2024 | Project Manager |
| Dec 18, 2024 | Bio Team Review for Completeness |
| Jan 08, 2025 | HPHC Historical Preservation No Effect |
| Feb 13, 2025 | Correspondence Received |
| Feb 14, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Feb 21, 2025 | Typist for Processing |
| Feb 21, 2025 | Executive Sign Off |
| Feb 21, 2025 | Sent to Photo Copy |
| Feb 21, 2025 | Permit Approved |
| Feb 21, 2025 | Biologist Report |
| Feb 25, 2025 | Permit Mailed |
| Mar 24, 2025 | Land Evidence Date |