| Action Date | Action Description |
|---|---|
| Nov 13, 2024 | Assent Application Received |
| Nov 18, 2024 | Administrative Review for Completeness |
| Jan 06, 2025 | Bio Team Review for Completeness |
| Jan 07, 2025 | Deficient Application - Owner Notification Sent |
| Jan 09, 2025 | Additional Information Received |
| Jan 27, 2025 | Deficiency Response Received |
| Feb 07, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Aug 19, 2025 | Application Accepted |
| Aug 19, 2025 | Project Manager |
| Aug 19, 2025 | Bio Team Review for Completeness |
| Aug 25, 2025 | HPHC Historical Preservation No Effect |
| Sep 08, 2025 | Biologist Report |
| Sep 10, 2025 | Typist for Processing |
| Sep 10, 2025 | Executive Sign Off |
| Sep 10, 2025 | Sent to Photo Copy |
| Sep 10, 2025 | Permit Approved |
| Sep 10, 2025 | Dock Post-Construction Certification by Engineer Required. |
| Sep 12, 2025 | Permit Mailed |
| Sep 16, 2025 | Land Evidence Date |