| Action Date | Action Description |
|---|---|
| Engineering Report | |
| Jan 14, 2025 | Maintenance Certification Request |
| Jan 22, 2025 | Administrative Review for Completeness |
| Feb 04, 2025 | Eng Team Review for Completeness |
| Feb 04, 2025 | Deficient Application - Owner Notification Sent |
| May 05, 2025 | Correspondence Received |
| Aug 07, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Aug 20, 2025 | Deficiency Response Received |
| Sep 03, 2025 | Eng Team Review for Completeness |
| Sep 03, 2025 | Application Accepted |
| Sep 03, 2025 | Project Manager |
| Sep 25, 2025 | HPHC Historical Preservation No Effect |
| Oct 03, 2025 | Additional Information Received |
| Oct 15, 2025 | 30 day Public Notice Issued |
| Oct 22, 2025 | Correspondence Received |
| Nov 14, 2025 | Public Notice End Date |