| Action Date | Action Description |
|---|---|
| Jan 22, 2025 | Preliminary Determination Request (Coastal) |
| Jan 28, 2025 | Administrative Review for Completeness |
| Feb 21, 2025 | Assent Application Received |
| Feb 24, 2025 | Application Accepted |
| Feb 24, 2025 | Bio Team Review for Completeness |
| Feb 24, 2025 | Project Manager |
| Mar 21, 2025 | HPHC Historical Preservation No Effect |
| Mar 27, 2025 | Objections/Comments Received |
| Apr 30, 2025 | Biologist Report |
| May 02, 2025 | Typist for Processing |
| May 02, 2025 | Executive Sign Off |
| May 02, 2025 | Sent to Photo Copy |
| May 02, 2025 | Permit Approved |
| May 06, 2025 | Permit Mailed |