| Action Date | Action Description |
|---|---|
| Jan 23, 2025 | Maintenance Certification Request |
| Jan 29, 2025 | Administrative Review for Completeness |
| Jan 31, 2025 | Bio Team Review for Completeness |
| Jan 31, 2025 | Project Manager |
| Jan 31, 2025 | Application Accepted |
| Mar 17, 2025 | HPHC Historical Preservation No Effect |
| Mar 21, 2025 | Biologist Report |
| Mar 27, 2025 | Typist for Processing |
| Mar 27, 2025 | Executive Sign Off |
| Mar 27, 2025 | Sent to Photo Copy |
| Mar 27, 2025 | Permit Approved |
| Mar 31, 2025 | Permit Mailed |
| May 29, 2025 | Land Evidence Date |
| Jul 18, 2025 | Additional Information Received |