| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer received. | |
| Feb 12, 2025 | Assent Application Received |
| Feb 19, 2025 | Administrative Review for Completeness |
| Feb 25, 2025 | Eng Team Review for Completeness |
| Feb 25, 2025 | Project Manager |
| Feb 25, 2025 | Application Accepted |
| Mar 31, 2025 | 30 day Public Notice Issued |
| Apr 29, 2025 | HPHC Historical Preservation No Effect |
| Apr 30, 2025 | Public Notice End Date |
| Aug 18, 2025 | Engineering Report |
| Aug 20, 2025 | Typist for Processing |
| Aug 20, 2025 | Executive Sign Off |
| Aug 20, 2025 | Sent to Photo Copy |
| Aug 20, 2025 | Permit Approved |
| Aug 21, 2025 | Permit Mailed |