| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Feb 19, 2025 | Assent Application Received |
| Feb 24, 2025 | Administrative Review for Completeness |
| Mar 11, 2025 | Eng Team Review for Completeness |
| Mar 11, 2025 | Project Manager |
| Mar 11, 2025 | Application Accepted |
| Mar 11, 2025 | Category B assigned |
| Apr 10, 2025 | HPHC Historical Preservation No Effect |
| Apr 14, 2025 | 30 day Public Notice Issued |
| May 14, 2025 | Public Notice End Date |
| Jun 03, 2025 | Additional Information Received |
| Jun 03, 2025 | Supervisor Biologist SignOff |
| Jun 03, 2025 | Supervisor Engineer SignOff |
| Jun 03, 2025 | Engineering Report |
| Jun 04, 2025 | Executive Signoff of Staff Reports |
| Jun 23, 2025 | Mail Agenda Notice |
| Jul 22, 2025 | Council Approval Granted |
| Jul 22, 2025 | Semi-Monthly Meeting Date Scheduled |
| Aug 06, 2025 | Stipulation Package by Engineer |
| Aug 06, 2025 | Typist for Processing |
| Aug 06, 2025 | Executive Sign Off |
| Aug 06, 2025 | Permit Approved |
| Aug 08, 2025 | Permit Mailed |
| Sep 23, 2025 | Correspondence Received |