| Action Date | Action Description |
|---|---|
| Assent Requirement | |
| Feb 20, 2025 | Assent Application Received |
| Feb 25, 2025 | Administrative Review for Completeness |
| Feb 26, 2025 | Bio Team Review for Completeness |
| Feb 26, 2025 | Project Manager |
| Feb 26, 2025 | Application Accepted |
| Mar 27, 2025 | HPHC Historical Preservation Comments/Concerns |
| Apr 15, 2025 | HPHC No Objection |
| May 06, 2025 | Engineering Report |
| May 09, 2025 | Biologist Report |
| May 12, 2025 | Typist for Processing |
| May 12, 2025 | Executive Sign Off |
| May 12, 2025 | Sent to Photo Copy |
| May 12, 2025 | Permit Approved |
| May 16, 2025 | Permit Mailed |
| Jun 12, 2025 | Land Evidence Date |