| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer Required. | |
| Feb 20, 2025 | Assent Application Received |
| Feb 25, 2025 | Administrative Review for Completeness |
| Feb 26, 2025 | Bio Team Review for Completeness |
| Mar 05, 2025 | US Army Corps of Engineers Project Number received. |
| Mar 26, 2025 | Application Accepted |
| Mar 26, 2025 | Project Manager |
| Mar 26, 2025 | Eng Team Review for Completeness |
| Apr 10, 2025 | HPHC Historical Preservation No Effect |
| Jul 16, 2025 | 30 day Public Notice Issued |
| Aug 16, 2025 | Public Notice End Date |
| Oct 10, 2025 | Plans Received |
| Oct 15, 2025 | Plans Received |
| Oct 15, 2025 | Engineering Report |
| Oct 16, 2025 | Typist for Processing |
| Oct 16, 2025 | Executive Sign Off |
| Oct 16, 2025 | Sent to Photo Copy |
| Oct 16, 2025 | Permit Approved |
| Oct 17, 2025 | Permit Mailed |