| Action Date | Action Description |
|---|---|
| Mar 26, 2025 | Assent Application Received |
| Apr 01, 2025 | Administrative Review for Completeness |
| Apr 03, 2025 | Bio Team Review for Completeness |
| Apr 03, 2025 | Project Manager |
| Apr 03, 2025 | Application Accepted |
| May 07, 2025 | Biologist Report |
| Jul 07, 2025 | HPHC Historical Preservation No Effect |
| Jul 08, 2025 | Executive Sign Off |
| Jul 08, 2025 | Sent to Photo Copy |
| Jul 08, 2025 | Permit Approved |
| Jul 08, 2025 | Typist for Processing |
| Jul 09, 2025 | Permit Mailed |