| Action Date | Action Description |
|---|---|
| Mar 26, 2025 | CHA Worksheet received |
| Mar 26, 2025 | Assent Application Received |
| Apr 01, 2025 | Administrative Review for Completeness |
| Apr 07, 2025 | Bio Team Review for Completeness |
| Apr 07, 2025 | Project Manager |
| Apr 07, 2025 | Application Accepted |
| Apr 15, 2025 | Objections/Comments Received |
| Apr 15, 2025 | Entry of Appearance Received |
| Apr 16, 2025 | Objections/Comments Received |
| Apr 21, 2025 | Entry of Appearance Received |
| Apr 21, 2025 | Objections/Comments Received |
| May 27, 2025 | Additional Information Requested from Applicant |
| May 28, 2025 | HPHC Historical Preservation No Effect |
| Jun 24, 2025 | Additional Information Received |
| Jul 24, 2025 | Objection withdrawal received |
| Sep 02, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Sep 03, 2025 | Biologist Report |
| Sep 09, 2025 | Dock Post-Construction Certification by Engineer Required. |
| Sep 09, 2025 | Typist for Processing |
| Sep 09, 2025 | Executive Sign Off |
| Sep 09, 2025 | Sent to Photo Copy |
| Sep 09, 2025 | Permit Approved |
| Sep 10, 2025 | Permit Mailed |
| Oct 10, 2025 | Land Evidence Date |