| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer Required. | |
| Apr 18, 2025 | Assent Application Received |
| Apr 25, 2025 | Administrative Review for Completeness |
| May 02, 2025 | Bio Team Review for Completeness |
| May 02, 2025 | Project Manager |
| May 02, 2025 | Application Accepted |
| May 22, 2025 | HPHC Historical Preservation No Effect |
| Jun 25, 2025 | Additional Information Requested from Applicant |
| Jul 11, 2025 | Biologist Report |
| Jul 11, 2025 | 30 day Public Notice Issued |
| Aug 11, 2025 | Public Notice End Date |
| Aug 19, 2025 | Plans Received |
| Sep 05, 2025 | Dock Meeting -- Approval |
| Sep 17, 2025 | Biologist Report |
| Sep 22, 2025 | Dock Post-Construction Certification by Engineer Required. |
| Sep 22, 2025 | Typist for Processing |
| Sep 22, 2025 | Executive Sign Off |
| Sep 22, 2025 | Sent to Photo Copy |
| Sep 22, 2025 | Permit Approved |
| Sep 23, 2025 | Permit Mailed |
| Oct 01, 2025 | Land Evidence Date |